Thailand’s longest railway tunnel nears excavation finish ahead of planned 2028 opening

 ·  By JLIT Newsroom  ·  3 min read
LINEWhatsAppX

Excavation of the 6.2-kilometre Ngao Tunnel in Lampang is expected to finish in December, with passenger and freight services on the northern railway planned for 2028.

Excavation of Thailand’s longest railway tunnel is expected to finish in December, marking a major step towards the planned opening of the Den Chai–Chiang Rai–Chiang Khong railway in 2028.

The 6.2-kilometre Ngao Tunnel passes through mountainous terrain in Ngao district, Lampang province. Deputy Prime Minister and Transport Minister Phiphat Ratchakitprakarn presided over a tunnel breakthrough ceremony there on Wednesday, 11 November.

According to Khaosod English, just 24.30 metres remained to be excavated at the time of the ceremony. Work began on 22 December 2023, but finishing the excavation will not mean the tunnel is ready for trains.

Structural work and testing still to come

Once excavation is complete, construction will continue on the tunnel’s internal structures, railway systems and safety equipment. Inspections and testing will follow before services can begin.

Phiphat described the milestone as a significant achievement for Thailand’s railway infrastructure, pointing to the engineering challenges posed by the mountainous terrain and complex geology.

State Railway of Thailand governor Anan Phonimdaeng said the changing rock formations required specialised construction techniques and strict safety supervision. These formations include limestone and volcanic ash deposits.

The December excavation target is therefore an intermediate milestone. The planned start of passenger and freight services remains 2028, with further construction and commissioning work required in the meantime.

Geology brings additional safety checks

The Department of Rail Transport has stepped up inspections of the railway project, with particular attention to conditions inside the Ngao Tunnel, the Bangkok Post reported.

Department director-general Pichet Kunadhamraks said rock and soil quality needed close attention because of their effect on construction stability. Sections containing poor-quality rock require additional precautions.

The department has instructed the State Railway of Thailand to ensure contractors follow approved construction methods and safety measures. These include geological mapping of the tunnel face, detailed assessments of rock-wedge risks, monitoring rainfall and water pressure in rock fractures, and checking tunnel walls for movement.

Track laying inside the Ngao Tunnel is expected to begin in 2027.

A northern passenger and freight link

The tunnel forms part of a railway stretching about 323 kilometres through Phrae, Lampang, Phayao and Chiang Rai. The metre-gauge, double-track project will have 25 stations, excluding the existing Den Chai station.

For future passengers and businesses, the wider railway—not the tunnel excavation alone—is the key development. It is intended to improve passenger connections and freight transport in northern Thailand.

The project also includes bridges, overpasses and underpasses designed to eliminate road–rail crossings. The Department of Rail Transport has urged the railway operator to accelerate delayed construction and complete four container yards at Den Chai, Phayao, Pa Daet and Chiang Rai stations.

Those works, together with the tunnel’s remaining structural and railway systems work, form part of preparations for the targeted 2028 opening.

JLIT Editorial
Just Landed in Thailand

Explore more with JLIT

Cars & Driving in Thailand →

Share this storyLINEWhatsAppX

Explore more of Thailand

Interactive Map Route Planner HubMoving & Settling In HubDiving ThailandFamily, Kids & Entertainment HubNightlife & Dining Hub

Read next